The ongoing construction work on railroad crossings in Godfrey continues this week, but the end appears to be in sight.   The Humbert Road crossing in Alton was completed over the weekend and remains open, although there are frequent slow downs and some traffic stops due to the movement of equipment.  The entire project should be completed for the area by May 5, but some crossings will be opening this week.   Here is the updated scheduled for today:


Alby St. in Alton: Closed will open on the 26th.

Tolle St. in Godfrey: OPEN and complete

Pearl St. in Godfrey: Closed—will open at 7 a.m. on 25th.

Bethany in Godfrey: Closed

(Report courtesy of Roadsafe)